Case study · Edmonton · Repair yard
Muddy storage yard repaired with road base in Edmonton
Photographed on site — Edmonton, September 2026
Drag to compare
Before and after
Watch the whole job
The full job in 7 seconds. Drag to scrub.
A quick walk around the yard with the mud loaded out and the driveway graded.
The tricky bit
Oil-contaminated soil dealt with properly
Some of the soil had become contaminated from an oil spill. We cleaned it up, removed it and disposed of it correctly rather than covering it over.
How we did it
The job, start to finish
-
Muddy tracks through the yard
The access driveway between the containers and the dome shelter was marked with muddy tyre tracks.
-
Sloppy mud out
The sloppy mud was dug out and loaded up, getting the bad ground out before anything new went down.
-
Working around the yard
The driveway was levelled out alongside the boat and containers stored on site.
-
Graded toward the shelter
The driveway graded out, with fresh grading marks running toward the dome shelter and the green containers off to the left.
-
Road base compacted
Road base went down and was compacted, firm and even across the full run of the driveway.
The result
A firm, even access driveway
The yard access driveway came up firm and even. The mud and ruts are gone, the contaminated soil is removed and the compacted road base gives the yard staff and vehicles a safe, clean and usable surface to work on.
- Suburb
- Edmonton
- Job type
- Repair yard
- Surface
- Compacted road base
- Removed
- Oil-contaminated soil
- Completed
- 28 Sep 2026
Full job notes
From a muddy, rutted access track to a firm, compacted road base surface.
We were asked to come in and repair a yard at an industrial storage site in Edmonton. The access driveway ran between shipping containers, tank containers and a dome-roofed shelter. It was in bad shape. The surface was waterlogged, with soft churned mud and deep tyre ruts after rain, and the yard staff and vehicles had to work around it every day.
First up we removed all the sloppy mud. Some of the soil had become contaminated from an oil spill, so that was cleaned up, removed and disposed of correctly. We got the bad ground out before anything new went down.
From there we started levelling. One of the during shots shows the driveway graded out, with fresh grading marks running toward the dome shelter and the trailer and green containers sitting off to the left. Getting the levels right matters here. If the base isn't even, the ruts come straight back.
With the ground prepped, we laid road base and compacted it. The gravel went in firm and even across the full run of the driveway. A blue drum marked 5 and the yellow-framed tank containers sat along the right the whole time, so we worked the surface in around what was stored on site.
It's straightforward work, but it makes a difference to a working yard. Mud slows everyone down and oil-contaminated ground has to be dealt with properly, not just covered over.
We handle yard and ground repair work like this across the region. If you've seen our other jobs around town, this one sits alongside our other projects in Edmonton. We tidy up and leave the site ready to use.
Oil-contaminated soil removed
Some of the soil had become contaminated from an oil spill. We cleaned it up, removed it and disposed of it correctly rather than covering it over.
Compacted road base
After levelling we laid road base and compacted it, giving a firm gravel surface that holds up under vehicle traffic instead of rutting out.
Worked around a live yard
The driveway runs between shipping containers, tank containers and a dome shelter, with a boat and vehicles stored on site. We worked the surface in around what was there.
What was included
- Removed the sloppy mud from the yard access driveway
- Cleaned up and removed oil-contaminated soil and disposed of it correctly
- Levelled and graded the driveway
- Laid road base over the prepared ground
- Compacted the surface to a firm, even finish
- Left the area safe, clean and usable for yard staff and vehicles
Muddy, rutted yard?
Yard churned to mud after rain?
We dig out the bad ground, level it and lay compacted road base that holds up under vehicles.
Next project